QUANTITIES REQUIRED
- Plastering (CM 1:3) = 1.50 bags / 10 m2
- Plastering (CM 1:5) = 1.05 bags / 10 m2
- Ceiling Plastering (CM 1:3) = 48 kg / 10 m2
- Brickwork (CM 1:5) = 86 Kg / 10 m3
- Brick work (CM 1:6) 9" thick = 80.64 Kg / 10 m3
- Brick work (CM 1:3) 4'/2" thick = 15.46 Kg / 10 m3
- Lime for white washing = 10 Kg/100 m2
- Painting = l0 ltr/ 100 m2
- Distemper 1st coat = 6.5 Kg / 100 m2
- Distemper 2nd coat = 5.0 kg / 100 m2
- Snowcem 1 st coat - 30 Kg I 100 m;
- Snowcem 2 nd coat - 20 Kg 100 m:
- Paint ready mixed one coat - 10 hr /100 m2
- Weathering Course - 7.68 Kg/m2
- Flooring —8.10 kg / m2
- Pressed tiles for weathering course (CM 1:3)- 7.68 Kg / m2
- Granolithic floor finish - 8.10 Kg/10m2